The Journal, October 2005, page 50
This year has seen two particularly significant events in the field of standard forms for construction and engineering contracts. The Joint Contracts Tribunal (“JCT”) has published its new suite of JCT 2005 contracts, and the Institution of Civil Engineers (“ICE”) has published the third edition of the New Engineering Contract. Both of these contracts make changes to the existing contracts and also introduce new contracts to the JCT and NEC families.
The JCT contracts and their Scottish versions produced by the Scottish Building Contracts Committee (“SBCC forms”) are the most popular standard forms used for the construction of buildings. The new JCT 2005 suite revises and updates the contract forms, amalgamates certain of the forms and introduces brand new additional forms, as a simplification and tidying up process. In particular, the JCT 98 standard form local authorities and private editions have been merged to form the “Standard Building Contract”, which comes in versions with quantities, with approximate quantities and without quantities. These forms can be used where sectional completion is required.
On the design and build front, the new main contract is the “Design and Build Contract”, which again can be used by both private and local authority employers and can also allow for sectional completion. A notable feature of this contract is that it preserves the position under the existing “With Contractor’s Design” contract, in that the contractor is only required to complete the design for the works. As with previous versions, there is no single-point responsibility for design and construction. In fact, the demarcation in design responsibility between employer and contractor is now clearer in that the contractor is now stated not to be responsible for the contents of the employer’s requirements or for verifying the adequacy of any design contained within them. Therefore, as with prior editions of JCT, if the developer wishes to achieve true single-point responsibility and hold his design and build contractor responsible for all of the design and construction, he must amend the form to provide that the contractor is responsible for the whole of the design – not just for completing the design.
The old and familiar heading in clause 25, “Extensions of time”, has now gone, to be replaced with the more modern concept of “Adjustment of completion date”. This is a recognition that the parties may wish to agree to accelerate the works. Other changes to this area of the contract include a requirement that the architect is now required to state the time allocated to each relevant event. There is still a requirement to use best endeavours to prevent delay, but in the event that delay transpires, the contractor is to do all that may reasonably be required to the satisfaction of the employer to proceed with the works.
Perhaps one of the most radical changes to the terms of the new JCT contracts is the position on third party rights. The JCT Major Project Form introduced in 2003 envisaged some developers and their funders and tenants relying on a schedule of third party rights in place of the usual collateral warranties. This position relied on the provisions of the English law Contracts (Rights of Third Parties) Act. The Major Projects Form was intended for use by experienced developers and contractors. However, the JCT has now allowed for the option of a schedule of third party rights to be granted to named third parties in JCT 2005, in place of collateral warranties. In Scotland, the SBCC is hoping to produce Scottish versions of the JCT 2005 contracts by the end of the year. It remains to be seen what position the SBCC will take on third party rights. The Scottish Major Project Form follows the English lead and provides for a schedule of third party rights in favour of named third parties. The Contracts (Rights of Third Parties) Act does not apply in Scotland, so these third party rights depend on the common law (the ius quaesitum tertio). There is a great deal more uncertainty about the application of the ius quaesitum tertio. It is undoubtedly the case that developers, tenants and funders in Scotland will remain keen to receive collateral warranties.
This year’s second particularly significant event was the publication of the third edition of the New Engineering Contract (“NEC 3”).
The first edition of the NEC was published by the ICE in 1993, and was endorsed and supported by Sir Michael Latham in his Constructing the Team. The contract was renamed the “Engineering & Construction Contract” for its second edition, republished in 1995, at which time it was amended specifically to take account of Latham’s recommendations. The NEC is not intended purely for use in engineering projects – it is intended for use in a wide range of situations, and it has achieved widespread success. The form has been used in projects as prestigious as the Channel Tunnel Rail Link, Heathrow Terminal 5, NHS ProCure 21 and the Eden Project. NEC 3 has been recommended by the Office of Government Commerce for use by public sector construction procurers on their construction projects.
The ICE has described NEC 3 as representing an “evolutionary rather than revolutionary change” to the second edition, the emphasis being very much on sound project management principles and practices. The ethos of the contract has always been to encourage collaborative relationships amongst the parties to a project, on the basis that co-operative management of construction projects will reduce the risks inherent in developments – the contract has always sought to embrace many of the advantages of partnering-type procurement. This ethos is extended in NEC 3.
One of the key collaborative features of the NEC has been the requirement that the contractor and project manager give each other early warning of matters which could affect the cost, timescale or quality of the project. The contractor is encouraged to comply because failure to do so may reduce the payment to him for a related compensation event in that the project manager may assess the compensation event “as if” an early warning was given. Obvious matters requiring early warning would include design problems, discovery of unexpected ground conditions and bad weather. NEC 3 develops the use of the early warning system beyond its role in NEC 2. It does this by introducing the concepts of a “risk register” and “risk reduction meetings”. The risk register is a live document. Initially, it will contain risks identified in the contract data. However, any matters which are the subject of early warnings are added to the register and then discussed in risk reduction meetings, in order to solve the problems in question. This procedure allocates the actions needed for efficient management of specific risks and assists in identifying the time and cost consequences of risk events.
The other changes to the form include changes to the requirements for the provision of method statements, changes to the provisions for the extension of the defects correction period, new adjudication clauses and a controversial provision that the contractor cannot claim compensation for compensation events where it fails to give notice within eight weeks of becoming aware of the event in question.
However, probably the most interesting new feature of both NEC 3 and the new JCT 2005 suite is the introduction into both families of contracts of standard form framework agreements.
The concept of the framework agreement has its roots in the idea that the scope for innovation, improvement and learning in developments is greater if a production team can stay together for more than one project. Framework agreements are one method in particular which encourages long-term relationships. In practice, a framework agreement is an umbrella agreement put in place over a set term, under which specific packages of work can be instructed as they are required. Both the JCT 2005 and NEC 3 framework agreements incorporate partnering principles, such as obligations that the parties will act in a spirit of mutual trust and co-operation.
The introduction of the standard form framework agreements is another reflection of the general trend in modern procurement towards collaborative working, for the mutual benefit of the parties. However, that goal cannot be met simply by the professional institutions providing good quality standard forms. Parties in the construction industry must work to achieve that goal in the real world – and their legal advisers must help by encouraging collaborative forms of procurement and providing realistic and commercial drafting of contracts.
Calum McIver is an associate with DLA Piper, Edinburgh
Current Issue FeaturesBraving the stormHow different types of legal firm are coping with the current economic downturn, and how they see their future Civil justice: where next?An abridged version of the keynote address delivered to the conference on civil justice held in Edinburgh on 20 June Title Conditions Act: new registration proceduresNew procedures are in place for deeds intended to create new real burdens, to assist solicitors in complying with the requirement for dual registration Young lawyers rebornInterview with Scottish Young Lawyers Association President Maryam Labaki on SYLA's ambitions as it relaunches Shining some more light...Second part of overview of this year's Finance Act looks at the provisions on savings, pensions, residence/domicile and business taxes, among others Power to the tribunal?An advocate's and a solicitor's views of how the Scottish Government's proposed reforms to arbitration law might work in practice Piece by pieceA progress report from England & Wales on the setting up of the complex regulatory machinery under the Legal Services Act 2007 The poor in our midstInterview with Scottish Solicitors' Benevolent Fund convener Craig Bennet, who aims to raise awareness of the Fund so it can provide more help to those in need Current Issue ArticlesShifting sandsPresident's message: with economic issues dominating the profession's thoughts, the Society is taking steps to provide advice and support to those in need A rank bad ruleOpinion by two advocates that the Faculty's response to the OFT does its members a disservice by defending the cab rank rule and by resisting the use of ABS The Society's future role in complaints handlingA reminder, in the light of reactions to the first levy issued on behalf of the new Complaints Commission, of when and how the Society's responsibilities are changing Appreciation: Lord JohnstonReport of the tribute paid in court by the Lord President Professional Practice CommitteeNew guidelines on acting as a company director; and document control and file tracking Facing the lean yearsSome advice on how to pull through a recession and be ready for the next upturn, as word goes round of legal firms looking at staff cuts and other measures (part 1 of 2) It's a web 2.0 worldThe interactive nature of web 2.0 technology presents business opportunities, while posing new risks for those with inadequate precautions as to employee internet use Questions, questionsIn reviewing their risk profiles and risk controls, all firms might benefit from conducting a self-assessment by addressing questions put by some insurers elsewhere Bare necessitiesLatest criminal cases, including offensive weapons; Moorov rule; withdrawal of representation; evidence of a deceased; contempt of court by solicitor Coming on the blind sideA technical-sounding consultation, currently open for comments, covers some significant aspects of dispute resolution in employment Relocation, relocationA recent decision explores the matters to consider when one parent wants to relocate abroad along with their child Worse than the disease?Has the UK quietly outlawed "alternative" medicine through the Consumer Protection from Unfair Trading Regulations? Sleeping bountyThe Scottish Community Foundation has a scheme to breathe new life into dormant charitable trusts Scottish Solicitors' Discipline TribunalReports relating to Eileen Agnes Coogans; Zosia Marion Elizabeth Fraser; Annaline Webster; Ian Samuel Gerard Donnelly; Mark David Sheppard Website reviewsReviews of sites of organisations concerned with domain name disputes Book reviewsReview of Child and Family Law (Sutherland) Industry standardA survey south of the border suggests that in-house work in commerce and industry doesn't always match expectations - but most in-house lawyers expect to stay Meet the committeeProfile of In-house Lawyers Group committee member Sara Scott What's in a motto?A sample of In-house Lawyers Group members' notarial mottoes, collected by ILG secretary Tricia Sim Leasing by example"Green leases" appear to be some way off yet for the UK, but a Canadian model now published shows how they might work Good call?Reply to article questioning the Donald Trump planning application call-in argues that the decision is both competent and consistent with proper operation of the system Home reports - the practice questionsOpen letter over reservations as to the Society's proposed guidelines on the operation of home reports, in so far as they deal with conflict of interest |